Warning: Undefined array key "cod" in /home/c2500813/public_html/articulo/el-puente-de-sumalao-estara-habilitado-en-abril-y.php on line 24 Warning: Undefined array key "main" in /home/c2500813/public_html/articulo/el-puente-de-sumalao-estara-habilitado-en-abril-y.php on line 215 Warning: Trying to access array offset on value of type null in /home/c2500813/public_html/articulo/el-puente-de-sumalao-estara-habilitado-en-abril-y.php on line 215 Deprecated: round(): Passing null to parameter #1 ($num) of type int|float is deprecated in /home/c2500813/public_html/articulo/el-puente-de-sumalao-estara-habilitado-en-abril-y.php on line 215 Warning: Undefined array key "weather" in /home/c2500813/public_html/articulo/el-puente-de-sumalao-estara-habilitado-en-abril-y.php on line 216 Warning: Trying to access array offset on value of type null in /home/c2500813/public_html/articulo/el-puente-de-sumalao-estara-habilitado-en-abril-y.php on line 216 Warning: Trying to access array offset on value of type null in /home/c2500813/public_html/articulo/el-puente-de-sumalao-estara-habilitado-en-abril-y.php on line 216 Warning: Undefined array key "weather" in /home/c2500813/public_html/articulo/el-puente-de-sumalao-estara-habilitado-en-abril-y.php on line 217 Warning: Trying to access array offset on value of type null in /home/c2500813/public_html/articulo/el-puente-de-sumalao-estara-habilitado-en-abril-y.php on line 217 Warning: Trying to access array offset on value of type null in /home/c2500813/public_html/articulo/el-puente-de-sumalao-estara-habilitado-en-abril-y.php on line 217 Deprecated: ucfirst(): Passing null to parameter #1 ($string) of type string is deprecated in /home/c2500813/public_html/articulo/el-puente-de-sumalao-estara-habilitado-en-abril-y.php on line 217 Warning: Undefined array key "main" in /home/c2500813/public_html/articulo/el-puente-de-sumalao-estara-habilitado-en-abril-y.php on line 218 Warning: Trying to access array offset on value of type null in /home/c2500813/public_html/articulo/el-puente-de-sumalao-estara-habilitado-en-abril-y.php on line 218 Deprecated: round(): Passing null to parameter #1 ($num) of type int|float is deprecated in /home/c2500813/public_html/articulo/el-puente-de-sumalao-estara-habilitado-en-abril-y.php on line 218 Warning: Undefined array key "main" in /home/c2500813/public_html/articulo/el-puente-de-sumalao-estara-habilitado-en-abril-y.php on line 219 Warning: Trying to access array offset on value of type null in /home/c2500813/public_html/articulo/el-puente-de-sumalao-estara-habilitado-en-abril-y.php on line 219 Deprecated: round(): Passing null to parameter #1 ($num) of type int|float is deprecated in /home/c2500813/public_html/articulo/el-puente-de-sumalao-estara-habilitado-en-abril-y.php on line 219 Warning: Undefined array key "main" in /home/c2500813/public_html/articulo/el-puente-de-sumalao-estara-habilitado-en-abril-y.php on line 220 Warning: Trying to access array offset on value of type null in /home/c2500813/public_html/articulo/el-puente-de-sumalao-estara-habilitado-en-abril-y.php on line 220 Deprecated: round(): Passing null to parameter #1 ($num) of type int|float is deprecated in /home/c2500813/public_html/articulo/el-puente-de-sumalao-estara-habilitado-en-abril-y.php on line 220 Warning: Undefined array key "wind" in /home/c2500813/public_html/articulo/el-puente-de-sumalao-estara-habilitado-en-abril-y.php on line 221 Warning: Trying to access array offset on value of type null in /home/c2500813/public_html/articulo/el-puente-de-sumalao-estara-habilitado-en-abril-y.php on line 221 El puente de Sumalao estará habilitado en abril Y - Catamarca a Diario
Catamarca

El puente de Sumalao estará habilitado en abril Y

Tiene un avance físico de casi el 70%.

Los trabajos en la reparación del puente que conecta la Capital con Valle Viejo están avanzados y los encargados de la obra confirmaron que a mediados del mes de abril estará habilitado para su circulación.

El gobernador Raúl Jalil, junto al vicegobernador Rubén Dusso y la intendenta de Valle Viejo, Susana Zenteno, visitaron la obra donde trabajadoras y trabajadores les comentaron los trabajos que se llevan a cabo.

Emiliano Veliz, inspector de la obra, comentó que “la obra consiste en la reparación de estribos, fundiciones y la superestructura. Tiene un avance físico de casi el 70% y esperamos habilitarla a mediados de abril”.

“El paso del tiempo y las crecidas del río provocaron un deterioro en el puente, por ello, estas obras son de vital importancia para su mantenimiento y puesta en valor”, explicó Veliz.

Durante el recorrido también estuvieron presentes el ministro de Infraestructura y Obras Civiles, Juan Marchetti, y el director de Vialidad Provincial, Fernando Castillo.